Posted on: December 30, 2022

[ARCHIVED] Miami-Dade Construction Advisory

10 Construction Advisory December 30 2022

The next construction phase for the installation of the 36-inch water line along NW/NE 135 Street begins the week of January 2, 2023 when the contractor begins to install sidewalks and curbs along NE 135 Street between NE 12 Avenue and NE 16 Avenue. This phase is expected to be completed in six weeks. The contractor will also perform exploratory work at NE 16 Avenue. Please use caution when traveling in the area.


CLICK HERE for additional information